With a SNET constraint applied, the successor task cannot begin before the constraint date, even if (as shown here) the predecessor task is completed before the constraint date.
英
美
- 应用SNET限制后,即使在限制日期之前完成前置任务(如此处所示),后续任务也不能在限制日期之前开始。